Challenge:
Muntons PLC suffered a large fire which caused significant damage. This resulted in the shutting down of a key element of the production of malt. This well established company needed to continue working during the rebuild and therefore a considerate cooperative relationship was essential.
Solution:
This project was completed in two phases. Works comprised of rebuilding the malt bins and adding a new building. The structure of this build was unique and required a collaborative working relationship with the skilled engineers at Perega. A key factor of the works was running alongside a new 30 meter high malt production factory. This complex design required very talented workers who were able to recommission and rebuild to achieve a very complex design.
Working alongside operation
Confined
working space
Close working relationship
with Perega
Enabled machinery to be installed as factory progressed
Saving time.
The outcome
The rebuild was achieved to a high specification. This very unique operation was completed on time and to the high standard that the client desired. Adamco was able to maintain a great working relationship, which allowed the job to progress quickly and effectively.